Feasibility report V3
9 August 2026 · Rooftop PV
1 USD = ₺47.61 · Central Bank 07.08.2026

Generation–consumption matching and investment feasibility

This report compares the generation profile of the designed plant with the facility's consumption profile on an hourly netting basis, and presents the financial results together with the capital cost derived from the bill of materials. Energy prices are held internally in Turkish lira and converted to the report currency for display only.

Report details. Project: Untitled project · Project ID: new · Calculated: 09.08.2026 11:19:51 · Input fingerprint: FZ-F115F8B7
Synthetic consumption profile. No hourly meter data is available; the result is modelled from the selected operating regime and may be optimistic.
2,801.0 kWpInstalled DC capacity
3,108,978Annual generation kWh
500,000Annual consumption kWh
49.3%Consumption covered
$1,342,290Capital cost used in the model
$182,925Year 1 saving
7.5 yearsPayback
12.4%Internal rate of return
Sanity check. Unit capital cost $0.479/Wp sits in the lower part of the market band; verify the project-specific roof, fire and grid items. The purchase price $0.0868/kWh assumes a regulated tariff; if a bilateral supply agreement applies, use the actual contract price.
49%coverage8%self-consumption100%generation/consumption30%payback/lifetime

1System summary

Facility typeRooftopDC / AC capacity2,801.0 kWp / 2,241.0 kW
Module count and rating4,446 × 630 WDC/AC ratio1.25
Inverter count22Specific yield1,110 kWh/kWp
Generation source — Energy simulation: ENERGY.result · year. The 8,760-hour generation curve was used for financial netting.

2Consumption assumptions

Consumption annual total was entered. The "spread evenly over 24 hours" regime was used for hourly distribution, with a summer-weighted monthly seasonality. This is a model; the result may change once meter data is entered.

3Monthly energy summary · hourly calculation

Monthly generation, consumption and self-consumption (kWh)

0115,444230,887346,331461,775JanFebMarAprMayJunJulAugSepOctNovDecGenerationConsumptionSelf-consumption
MonthGeneration kWhConsumption kWhSelf-consumptionExported to gridImported from grid
January109,86728,22610,26799,60017,959
February146,81628,22611,775135,04116,451
March227,22532,25815,298211,92716,960
April312,61538,30619,615292,99918,691
May379,01746,37126,559352,45819,812
June415,32754,43531,754383,57322,681
July427,56960,48434,946392,62425,538
August381,19660,48431,971349,22528,512
September279,73750,40324,656255,08125,747
October192,61140,32317,610175,00122,713
November132,61932,25812,229120,39120,029
December104,37728,2269,91494,46318,312
Total3,108,978500,000246,5952,862,383253,405
Paid-energy check: Of the 2,862,383 kWh exported to the grid, 2,862,383 kWh is treated as paid and 0 kWh as above the limit and subject to system usage charges. No limit was applied owing to a verified exemption.

Self-consumption ratio: 7.9% of generation was consumed on site. Sensitivity scenario (not the headline result): with monthly netting the year 1 saving would be $189,437.

4Bill of materials and capital cost

Capital cost by category ($)

Solar equipment (modules and inverters)417,53231.1%Installation labour and services248,67818.5%Overheads and other169,98412.7%Structural works (mounting system)159,53711.9%DC cabling and connection104,1827.8%HV distribution centre and transformer87,2746.5%Earthing and lightning protection69,6945.2%Site civil works and infrastructure50,8353.8%LV switchboard and cabling28,7552.1%SCADA, monitoring and communications5,8180.4%
NoItemUnitQuantityUnit priceAmountShare
Solar equipment (modules and inverters)417,532
1PV module 630 Wpcs4,446.0068.81305,93522.8%
2String inverter ≈102 kW eachpcs22.005,072.62111,5988.3%
Structural works (mounting system)159,537
3Mounting profile (aluminium rail)m10,671.009.45100,8637.5%
4Mid clamppcs8,892.001.2611,2060.8%
5End clamppcs2,223.001.473,2690.2%
6Rail splicepcs1,557.002.003,1070.2%
7Roof mounting foot / sandwich-panel hookpcs7,114.003.6826,1501.9%
8Stainless bolt and nut setset17,784.000.8414,9421.1%
DC cabling and connection104,182
9DC solar cable 1×6 mm²m61,622.001.64100,9597.5%
10MC4 connector pairpair1,071.001.221,3050.1%
11DC surge arrester (SPD Type 2)pcs22.0050.411,1090.1%
12DC load break switchpcs22.0036.768090.1%
LV switchboard and cabling28,755
13AC power cable (NYY) NYY 3×70+35 · 400 V · ~155 A per inverterm1,210.0014.9118,0451.3%
14AC distribution boardpcs1.001,638.361,6380.1%
15AC moulded-case circuit breakerpcs22.00399.098,7800.7%
16AC surge arrester (SPD Type 2)pcs1.0060.91610.0%
17Bidirectional meterpcs1.00231.052310.0%
HV distribution centre and transformer87,274
18Dry-type power transformer ≈2500 kVApcs1.0070,890.7070,8915.3%
19MV switchgear (incomer / outgoing / metering / protection)set1.0016,383.6316,3841.2%
Earthing and lightning protection69,694
20Earthing conductor (copper 16–35 mm²)m12,605.005.0463,5434.7%
21Earth rodpcs47.0028.361,3330.1%
22Equipotential bonding barpcs1.0054.61550.0%
23Earthing clamp / exothermic weld kitpcs2,668.001.794,7630.4%
SCADA, monitoring and communications5,818
24Dataloggerpcs1.00546.125460.0%
25Power analyserpcs1.00189.041890.0%
26RS485 / communications cablem6,163.000.804,9190.4%
27Modem / router (4G)pcs1.00163.841640.0%
Site civil works and infrastructure50,835
28Cable duct / traym5,042.0010.0850,8353.8%
Installation labour and services248,678
29Mechanical installation labourkWp2,801.0029.4182,3686.1%
30Electrical installation labourkWp2,801.0024.1667,6595.0%
31Transport and on-site handlingkWp2,801.0010.9230,5942.3%
32Design and engineering serviceskWp2,801.0017.8550,0093.7%
33Grid connection and authority approval feesproject1.001,785.401,7850.1%
34Commissioning and testingproject1.00966.219660.1%
35Health and safety and site organisationkWp2,801.005.4615,2971.1%
Overheads and other169,984
36Contingencyproject1.0029,307.6329,3082.2%
37EPC margin and overheadsproject1.00140,676.64140,67710.5%
TOTAL CAPITAL COST1,342,290100%

Capital cost per kWp: $479/kWp · Conversion: 1 USD = ₺47.61 · Central Bank 07.08.2026

5Financial result and unit price check

$0.0868Grid purchase price / kWh
$0.0611Paid export price / kWh
$0.0000System usage charge above limit / kWh
$0Total cost above limit
Assumptions — purchase $0.0868/kWh · gross export $0.0611/kWh · paid export $0.0611/kWh (single-rate active energy price for the customer group, EPDK, 4 April 2026) · O&M 1.0% of capital per year · module degradation 0.55%/year · energy price escalation 0.0%/year · O&M escalation 0.0%/year · discount rate 12.0% · lifetime 25 years.
Purchase price source — EPDK regulated tariff, 4 April 2026.
Tariff source — Purchase price: EPDK 4 April 2026 · MV single-rate · Industrial (active energy 290.9687 + distribution 118.2457 kr/kWh; including electricity consumption tax, excluding VAT = ₺4.1331/kWh) · EPDK — Electricity Tariff Tables (https://epdk.gov.tr/Detay/Icerik/3-0-1/tarifeler). If prices have been edited manually, this note shows only the source of the default.
Netting source — EPDK Board Decision no. 14531 · Official Gazette 05.05.2026 / 33244 (https://epdk.gov.tr/Detay/Icerik/3-0-92/lisanssiz-uretim). The decision came into force on 5 May 2026; the 2026 unlicensed-generation limit notification was issued as of 1 June 2026.

Cumulative cash flow (25 years)

-1,598,034-404,560788,9151,982,3893,175,8640510152025Payback 7.5 yearsCumulative cash · $
YearGeneration kWhNet cash $Cumulative $
00-1,342,290-1,342,290
13,108,978182,925-1,159,365
23,091,878181,845-977,519
33,074,873180,771-796,748
43,057,961179,703-617,045
53,041,142178,641-438,404
63,024,416177,585-260,820
73,007,782176,534-84,286
82,991,239175,48991,203
92,974,787174,450265,654
102,958,426173,417439,071
112,942,155172,389611,460
122,925,973171,367782,827
132,909,880170,351953,178
142,893,876169,3401,122,518
152,877,959168,3351,290,853
162,862,130167,3351,458,189
172,846,389166,3411,624,530
182,830,734165,3521,789,883
192,815,165164,3691,954,252
202,799,681163,3912,117,643
212,784,283162,4192,280,062
222,768,969161,4522,441,514
232,753,740160,4902,602,004
242,738,594159,5332,761,537
252,723,532158,5822,920,119
$36,781Net present value
12.4%Internal rate of return
$0.06Unit cost /kWh
7.5 yearsSimple payback

6Method, regulation and data quality

Netting regime

Generation and consumption were compared separately for every hour. Board Decision no. 14531 came into force on 5 May 2026; the 2026 unlicensed-generation limit notification was issued as of 1 June 2026.

Purchase price

Derived from the active energy and distribution charges for the selected customer group, with the selected tax treatment.

Export price

The single-rate active energy price for the selected customer group was used. No further distribution deduction was applied to the paid export price.

Paid generation limit

No limit was applied; this was selected as a user-verified exemption.

Currency consistency

Tariff, export and fixed O&M values are held in Turkish lira. Finance and capital cost were converted to USD together at 1 USD = ₺47.61 · Central Bank, 07.08.2026.

Method and limitations. The generation curve is taken from the application's hourly energy simulation. The consumption profile is based on the regime assumption stated above. Material quantities are preliminary values derived from engineering ratios per kWp; the definitive bill of quantities is prepared for the specific project. Prices are entered by the user and do not constitute an offer. Grid connection conditions, distribution charges and netting regulations vary by region and date; this report is not a binding commitment.

solarsimpro · GUNESUZ Enerji Proje Danışmanlık Tic. Ltd. Şti. · SolarSimPro solarsimpro.com