SolarSimPro
Feasibility report V3
9 August 2026 · Ground-mounted PV
1 USD = ₺47.61 · Central Bank 07.08.2026

Generation–consumption matching and investment feasibility

This report compares the generation profile of the designed plant with the facility's consumption profile on an hourly netting basis, and presents the financial results together with the capital cost derived from the bill of materials. Energy prices are held internally in Turkish lira and converted to the report currency for display only.

Report details. Project: Untitled project · Project ID: new · Calculated: 09.08.2026 10:53:43 · Input fingerprint: FZ-B78EDE56
Synthetic consumption profile. No hourly meter data is available; the result is modelled from the selected operating regime and may be optimistic.
3,063.1 kWpInstalled DC capacity
4,763,594Annual generation kWh
5,000,000Annual consumption kWh
64.7%Consumption covered
$1,740,254Capital cost used in the model
$356,823Year 1 saving
4.9 yearsPayback
19.7%Internal rate of return
Sanity check. Unit capital cost $0.568/Wp sits in the lower part of the market band; verify the project-specific roof, fire and grid items. The purchase price $0.0868/kWh assumes a regulated tariff; if a bilateral supply agreement applies, use the actual contract price.
65%coverage68%self-consumption95%generation/consumption20%payback/lifetime

1System summary

Facility typeGround-mountedDC / AC capacity3,063.1 kWp / 2,450.0 kW
Module count and rating4,862 × 630 WDC/AC ratio1.25
Inverter count25Specific yield1,555 kWh/kWp
Generation source — Energy simulation: ENERGY.result · year. The 8,760-hour generation curve was used for financial netting.

2Consumption assumptions

Consumption annual total was entered. The "office hours (08:00–18:00)" regime was used for hourly distribution, with a flat monthly seasonality. This is a model; the result may change once meter data is entered.

3Monthly energy summary · hourly calculation

Monthly generation, consumption and self-consumption (kWh)

0159,401318,802478,203637,604JanFebMarAprMayJunJulAugSepOctNovDecGenerationConsumptionSelf-consumption
MonthGeneration kWhConsumption kWhSelf-consumptionExported to gridImported from grid
January181,312424,658162,45018,862262,208
February257,620383,562209,02748,593174,535
March359,101424,658275,48883,613149,170
April423,947410,959298,294125,653112,665
May488,616424,658329,050159,56695,608
June542,191410,959331,516210,67579,442
July590,374424,658344,784245,58979,873
August563,354424,658333,384229,97091,273
September502,927410,959304,679198,248106,280
October394,384424,658273,288121,096151,369
November276,813410,959211,39865,415199,561
December182,954424,658160,10522,849264,552
Total4,763,5945,000,0003,233,4631,530,1301,766,537
Paid-energy check: Of the 1,530,130 kWh exported to the grid, 1,530,130 kWh is treated as paid and 0 kWh as above the limit and subject to system usage charges. No limit was applied owing to a verified exemption.

Self-consumption ratio: 67.9% of generation was consumed on site. Sensitivity scenario (not the headline result): with monthly netting the year 1 saving would be $380,607.

4Bill of materials and capital cost

Capital cost by category ($)

Solar equipment (modules and inverters)456,65026.2%Structural works (mounting system)339,93219.5%Installation labour and services271,76915.6%Overheads and other220,38212.7%Site civil works and infrastructure141,7768.1%DC cabling and connection114,0136.6%HV distribution centre and transformer92,9465.3%Earthing and lightning protection76,2264.4%LV switchboard and cabling20,2831.2%SCADA, monitoring and communications6,2780.4%
NoItemUnitQuantityUnit priceAmountShare
Solar equipment (modules and inverters)456,650
1PV module 630 Wpcs4,862.0068.81334,56019.2%
2String inverter ≈98 kW eachpcs25.004,883.58122,0907.0%
Structural works (mounting system)339,932
3Mounting profile (aluminium rail)m11,669.009.45110,2966.3%
4Mid clamppcs9,724.001.2612,2550.7%
5End clamppcs2,431.001.473,5740.2%
6Rail splicepcs1,702.002.003,3960.2%
7Table foot / pile (ground-mounted)pcs876.0030.4626,6801.5%
8Table beam and cross bracing ≈17.6 kWp/masaset174.00962.01167,3909.6%
9Stainless bolt and nut setset19,448.000.8416,3400.9%
DC cabling and connection114,013
10DC solar cable 1×6 mm²m67,388.001.64110,4066.3%
11MC4 connector pairpair1,172.001.221,4280.1%
12DC surge arrester (SPD Type 2)pcs25.0050.411,2600.1%
13DC load break switchpcs25.0036.769190.1%
LV switchboard and cabling20,283
14AC power cable (NYY) NYY 4×25+16 · 800 V · ~74 A per inverterm1,375.006.098,3760.5%
15AC distribution boardpcs1.001,638.361,6380.1%
16AC moulded-case circuit breakerpcs25.00399.099,9770.6%
17AC surge arrester (SPD Type 2)pcs1.0060.91610.0%
18Bidirectional meterpcs1.00231.052310.0%
HV distribution centre and transformer92,946
19Dry-type power transformer ≈2700 kVApcs1.0076,561.9676,5624.4%
20MV switchgear (incomer / outgoing / metering / protection)set1.0016,383.6316,3840.9%
Earthing and lightning protection76,226
21Earthing conductor (copper 16–35 mm²)m13,784.005.0469,4874.0%
22Earth rodpcs52.0028.361,4750.1%
23Equipotential bonding barpcs1.0054.61550.0%
24Earthing clamp / exothermic weld kitpcs2,918.001.795,2100.3%
SCADA, monitoring and communications6,278
25Dataloggerpcs1.00546.125460.0%
26Power analyserpcs1.00189.041890.0%
27RS485 / communications cablem6,739.000.805,3790.3%
28Modem / router (4G)pcs1.00163.841640.0%
Site civil works and infrastructure141,776
29Perimeter fence (mesh, with posts)m767.0039.9130,6101.8%
30Site entrance gatepcs1.00882.208820.1%
31Cable duct / traym5,514.0010.0855,5933.2%
32Cable trench (cut and fill)m7,658.007.1454,6903.1%
Installation labour and services271,769
33Mechanical installation labourkWp3,064.0029.4190,1025.2%
34Electrical installation labourkWp3,064.0024.1674,0124.3%
35Transport and on-site handlingkWp3,064.0010.9233,4661.9%
36Design and engineering serviceskWp3,064.0017.8554,7053.1%
37Grid connection and authority approval feesproject1.001,785.401,7850.1%
38Commissioning and testingproject1.00966.219660.1%
39Health and safety and site organisationkWp3,064.005.4616,7331.0%
Overheads and other220,382
40Contingencyproject1.0037,996.8137,9972.2%
41EPC margin and overheadsproject1.00182,384.71182,38510.5%
TOTAL CAPITAL COST1,740,254100%

Capital cost per kWp: $568/kWp · Conversion: 1 USD = ₺47.61 · Central Bank 07.08.2026

5Financial result and unit price check

$0.0868Grid purchase price / kWh
$0.0611Paid export price / kWh
$0.0000System usage charge above limit / kWh
$0Total cost above limit
Assumptions — purchase $0.0868/kWh · gross export $0.0611/kWh · paid export $0.0611/kWh (single-rate active energy price for the customer group, EPDK, 4 April 2026) · O&M 1.0% of capital per year · module degradation 0.55%/year · energy price escalation 0.0%/year · O&M escalation 0.0%/year · discount rate 12.0% · lifetime 25 years.
Purchase price source — EPDK regulated tariff, 4 April 2026.
Tariff source — Purchase price: EPDK 4 April 2026 · MV single-rate · Industrial (active energy 290.9687 + distribution 118.2457 kr/kWh; including electricity consumption tax, excluding VAT = ₺4.1331/kWh) · EPDK — Electricity Tariff Tables (https://epdk.gov.tr/Detay/Icerik/3-0-1/tarifeler). If prices have been edited manually, this note shows only the source of the default.
Netting source — EPDK Board Decision no. 14531 · Official Gazette 05.05.2026 / 33244 (https://epdk.gov.tr/Detay/Icerik/3-0-92/lisanssiz-uretim). The decision came into force on 5 May 2026; the 2026 unlicensed-generation limit notification was issued as of 1 June 2026.

Cumulative cash flow (25 years)

-2,239,95691,9872,423,9314,755,8747,087,8170510152025Payback 4.9 yearsCumulative cash · $
YearGeneration kWhNet cash $Cumulative $
00-1,740,254-1,740,254
14,763,594356,823-1,383,431
24,737,394354,765-1,028,666
34,711,338352,718-675,949
44,685,426350,682-325,266
54,659,656348,65823,391
64,634,028346,644370,036
74,608,541344,642714,678
84,583,194342,6511,057,329
94,557,986340,6711,397,999
104,532,917338,7011,736,700
114,507,986336,7432,073,443
124,483,192334,7952,408,238
134,458,535332,8582,741,095
144,434,013330,9313,072,027
154,409,626329,0153,401,042
164,385,373327,1103,728,152
174,361,253325,2154,053,368
184,337,266323,3314,376,698
194,313,411321,4574,698,155
204,289,688319,5935,017,749
214,266,094317,7405,335,488
224,242,631315,8965,651,385
234,219,296314,0635,965,448
244,196,090312,2406,277,688
254,173,012310,4276,588,115
$952,320Net present value
19.7%Internal rate of return
$0.05Unit cost /kWh
4.9 yearsSimple payback

6Method, regulation and data quality

Netting regime

Generation and consumption were compared separately for every hour. Board Decision no. 14531 came into force on 5 May 2026; the 2026 unlicensed-generation limit notification was issued as of 1 June 2026.

Purchase price

Derived from the active energy and distribution charges for the selected customer group, with the selected tax treatment.

Export price

The single-rate active energy price for the selected customer group was used. No further distribution deduction was applied to the paid export price.

Paid generation limit

No limit was applied; this was selected as a user-verified exemption.

Currency consistency

Tariff, export and fixed O&M values are held in Turkish lira. Finance and capital cost were converted to USD together at 1 USD = ₺47.61 · Central Bank, 07.08.2026.

Method and limitations. The generation curve is taken from the application's hourly energy simulation. The consumption profile is based on the regime assumption stated above. Material quantities are preliminary values derived from engineering ratios per kWp; the definitive bill of quantities is prepared for the specific project. Prices are entered by the user and do not constitute an offer. Grid connection conditions, distribution charges and netting regulations vary by region and date; this report is not a binding commitment.

solarsimpro · GUNESUZ Enerji Proje Danışmanlık Tic. Ltd. Şti. · SolarSimPro solarsimpro.com